The 2026 Sidewalk and Concrete Replacement Program is focused on enhancing pedestrian safety and accessibility. It includes the removal and reconstruction of damaged concrete sidewalks, curbs, gutters, and driveway approaches in neighborhoods along Thousand Oaks Blvd. and Westlake Blvd., as shown on the location maps below.


This year’s project is expected to repair approximately 160 curb ramps to meet ADA accessibility standards, 15,000 square feet of concrete sidewalk, 5,400 square feet of driveway aprons, and 1,560 linear feet of curb and gutter.

Project Timeframe

Construction is expected to occur from February through summer 2026.


Areas on the table can be identified on the Project Maps below.

Dates are subject to change.


Location/Task

Duration

Start

Finish

Citywide




DEMO, FINE GRADE, AND POUR

10 days

2/24/26

3/9/26

BACKFILL SLOT PATCH AND CONCRETE

1 day

3/10/26

3/10/26

PAVE SLOT PATCHES

2 days

3/11/26

3/12/26

REMOVE BMP'S

1 day

3/12/26

3/12/26

Area 2 Auto Mall




DEMO, FINE GRADE, AND POUR

5 days

3/11/26

3/17/26

BACKFILL SLOT PATCH AND CONCRETE

1 day

3/18/26

3/18/26

LANDSCAPE AND IRRIGATION RESTORATION WORK

1 day

3/18/26

3/18/26

PAVE SLOT PATCHES

1 day

3/19/26

3/19/26

REMOVE BMP'S

1 day

3/19/26

3/19/26

Area 3 Near Russell Park




DEMO, FINE GRADE, AND POUR

12 days

3/19/26

4/3/26

BACKFILL SLOT PATCH AND CONCRETE

2 days

4/6/26

2/7/26

LANDSCAPE AND IRRIGATION RESTORATION WORK

2 days

4/6/26

4/7/26

PAVE SLOT PATCHES

1 day

4/8/26

4/8/26

REMOVE BMP'S

1 day

4/8/26

4/8/26

Area 4 Near S. Westlake Blvd & Devonshire Ct




DEMO, FINE GRADE, AND POUR

7 days

4/8/26

4/16/26

BACKFILL SLOT PATCH AND CONCRETE

1 day

4/17/26

4/17/26

LANDSCAPE AND IRRIGATION RESTORATION WORK

1 day

4/17/26

4/17/26

PAVE SLOT PATCHES

1 day

4/20/26

4/20/26

REMOVE BMP'S

1 day

4/20/26

4/20/26

Area 1 T.O. Blvd & Lombard St




DEMO, FINE GRADE, AND POUR

8 days

4/20/26

4/29/26

BACKFILL SLOT PATCH AND CONCRETE

1 day

4/30/26

4/30/26

LANDSCAPE AND IRRIGATION RESTORATION WORK

1 day

4/30/26

4/30/26

PAVE SLOT PATCHES

1 day

5/1/26

5/1/26

REMOVE BMP'S

1 day

5/1/26

5/1/26

Area 5 Near Autozone Parking Lot




DEMO, FINE GRADE, AND POUR

2 days

5/1/26

5/4/26

BACKFILL SLOT PATCH AND CONCRETE

1 day

5/5/26

5/5/26

LANDSCAPE AND IRRIGATION RESTORATION WORK

1 day

5/5/26

5/5/26

PAVE SLOT PATCHES

1 day

5/6/26

5/6/26

REMOVE BMP'S

1 day

5/6/26

5/6/26

PUNCH LIST

6 days

5/7/26

5/14/26


Funding

The City is in the process of awarding the construction contract. This project is funded by the Gas Tax Fund.

Project Benefits

Repairing or replacing damaged concrete sidewalks, curbs, gutters, and driveway approaches improves pedestrian access and street drainage. Priority is given to the areas with higher pedestrian traffic, schools, public facilities, and connecting walkways.


Project Impacts

  1. Streets will have partial lane closures, and some will have full driveway closures with limited access. Businesses/Residents will receive a 72-hour advance notification for any full driveway closure.
  2. There will be temporary traffic control restrictions and extra delays due to construction.
  3. The public is asked to allow extra time and exercise caution while traveling and walking through the construction area.
  4. “No Parking” Signs will be posted 72 hrs. in advance of the work.
  5. Residents will be notified 7 days in advance of the work.