Conejo Canyons Bridge
CI 5527
The project includes construction of a steel bridge across the Arroyo Conejo Creek southwest of Hill Canyon Road in the Conejo Canyons Open Space area (COSCA). The construction of the bridge was identified as a high priority project for improving public access and is a key component of the trail system in the Conejo Canyons Open Space. It connects existing trails on either side of the creek and is a key link between Conejo Canyons and Wildwood Park.
The California Department of Fish and Wildlife (CDFW) permit requires a comprehensive post-construction habitat restoration phase to commence following the completion of the br
Timeline and Funding
The bridge construction started in September 2023 and was completed in April 2024. The post-construction habitat restoration phase will start in September 2024.
The total estimated project cost is $3,200,000 and is included in the adopted FY 2021-23 Capital Improvement Budget. The total cost will be partially offset by donation from Conejo Open Space Foundation and contribution from Conejo Recreation and Park District.